Some of the major Projects for which material investigations and tests have been undertaken by Saba Engineering are listed below

Sr. No.

Project

Client

Duration

1

New office compound

British Embassy

March, 1994

2

Sodo – Arbaminch Road

Dana Consult

June, 1995

3

Addis Ababa – Gedo Road Project

Beller Consult Gmbh

February, 1996

4

Jimma – Bonga – Mizan Road

O’sulivan & Etham Limited International

August, 1996

5

Alemgenna – Hossana – Sodo Road upgrading

C/O Wadsam Geotech, Stewart Scott International Consulting Engineers

May, 1997 & July, 1997

6

Nazreth - Assella – Dodolla Road

Dana Consult

June 1997

7

Shashemene – Goba road upgrading

Dana Consult

August, 1997

8

Nekemt – Ghimbi Road

Wadsam Geotec Plc.

Oct, 1997

9

Nejo – Assosa Road

Wadsam Geotec Plc.

November, 1997

10

Mazoria – Durame – Durgi Road

Panaf Consult

December, 1997

11

Woldia – Woreta Road Upgrading

Louis Berger International Inc.

January, 1998 & February, 1998

12

Modjo – Awash – Mille Road

Nor Consult

February, 1998

13

Sub Arterial Asphalt Road & RR50 Standard Road

Harar Works & Development Bureau

February, 1998

14

Arbaminch – Jinka Road

THAL Consult

February, 1998

15

Wacha – Maji Road

Gannett Fleming

February, 1998

16

Shek Husen – Wabe Road

National Consultants

March, 1998

17

Gondar – Humera Road

Sheladia Associates Inc.

April, 1998

18

Bonga – Ameya – Chida Road

Sauti Consulting Engineers

April, 1998

19

Dera – Mechara Road

Wilbur Smith Associates

July, 1998

20

Busunju – Kiboga – Homia Road upgrading Project, UGANDA

Sauti Consulting Engineers

February – April 1998& April – May 1999.

21

Addis Ababa Ring Road Project

CRBC

Since 1998

22

Addis – Modjo – Awassa & Addis Jimma Road projects.

DRAGADOS & J&P joint venture

Since 1998